Module 11 Closure
***Q. I think the major disadvantage of a computerized system is the "hands-off" 
  approach that PM's might take. Since the computer does all the work for you, 
  it is very easy to enter all the project data into the computer and then ignore 
  the results, where as a manual approach forces you to study the results because 
  you formulate them yourself. Using a computerized approach it is also much easier 
  to miss mistakes or shortcomings if you don't carefully study the computer output. 
  
  A. Good answer and very true. One important way to bridge the gap is to have 
  the PM always write a cover letter or executive summary to the computerized 
  report. At least then the PM will usually read the material. 
***Q. About using the existing company MIS and setting up a PMIS.
  A. The alternative to the PMIS is to use the company's existing MIS. These are 
  often accounting systems for generating financial statement, not reports useful 
  for controlling projects. See (Module 
  7 Cost Accounting ). The existence of a "project" almost always 
  indicates it is separate from the companies standard accounting systems (unless 
  the company only does projects).
**Q. The muddiest part of this chapter was the discussion of variances and 
  indices. I still have a difficult time differentiating between budgeted cost 
  of work performed (BCWP) and budgeted cost of work scheduled (BCWS). I thought 
  the book did not explain very well how to differentiate between these two values. 
  
  A. Your book presents a number of different techniques for wresting with the 
  problem of a three-dimensional problem (cost, schedule, production) into a two 
  dimensional representation, usually time vs. cost or production. Many projects 
  will have hundreds of work tasks, each with a budget. As the project goes on, 
  each individual task will have its cost. If you had all discrete tasks and the 
  nature of the tasks were that they were either 0% or 100% complete, you would 
  sum up all the costs for the tasks done (ACWP) and their budgets (BCWP). (Note 
  that the foregoing says nothing about schedule.) Now if you took the schedule 
  for these tasks you could determine a cumulative budget that was planned to 
  be spent. This is the BCWS. Look at Figure 10-6 after you have worked with the 
  problems that may clarify things. 
***Q. Dr. Perkins: Obviously, withholding negative information is mostly wrong 
  and unethical but what about delaying such news? At what point does delaying 
  bad news in an effort to soften the blow become unethical?
  A. Wow. (This will not be on the final) There is a big difference between telling 
  a lie and not telling the truth. It is never right to lie by writing or saying 
  something you know is not true, or expressing something a fact that you are 
  not sure is a fact. Not telling the truth means keeping your mouth shut. This 
  is often quite appropriate. The dilemma comes when I have some sort of obligation 
  to report something that I don't want to. The question often is, can I delay 
  this without falsifying something? As a young engineer, I worked for a superintendent, 
  Harry, who was a pretty good fellow, but from time to time would ask me to tell 
  a lie on his behalf. I handled it by telling the client the lie, but expressing 
  it as, "Harry told me to tell you
." Which was the truth. When 
  the sharp client perceived the problem and asked me, "Perkins what do you 
  think?" I answered, "I can't tell you that." Today, I would simply 
  tell Harry to get someone else to tell it. I should mention that the lies were 
  not significant nor an attempt to steal or fraud, just to get the client off 
  our backs while we scrambled to fix what was broken. 
Q. Do you think that with the increasing focus toward computers that we will 
  see a larger emphasis toward mathematical optimization approaches? 
  A. It depends on the industry. In many industries, optimization is the rule. 
  In the construction industry it has always been done a low level and advanced 
  OR was not needed. The cases where optimization was most often used in construction 
  were, unfortunately, in lawsuits where one side was trying to prove that the 
  other side did not use the best methods or make the correct decisions. 
Q. I need some remedial instruction on milestone reporting. The figures the 
  author uses (pg 435 and 436) are strange. I don't see the management benefit 
  of this report or diagram. Perhaps you could elaborate in the closure module. 
  
  A. Yes, it is very elaborate and is in fact a different system, analogous to 
  Gantt charts. Here the company apparently does "projects" but the 
  projects have very similar steps. Note that someone initials the completion 
  of each step. Also, revisions are dated. Hence this is a method of controlling 
  work, as well as charting milestones.